Coastal Utilities

utility
C-0002 ยท Gulf Coast, TX ยท owner Mark Reyes ยท active
Contacts & relationships
Ron Diazprimary
Director of Generation ยท economic
Lily Tran
Maintenance Lead ยท champion
Activity & next actions
taskSend final proposal to Ron2026-06-29
Performance with this client3 jobs ยท $7.8M ยท avg fade -5.5 pts
Completed jobValueBid marginActual marginFade
Midlothian U1 โ€” 7FA Hot Gas Path$2.9M13%3%-9.9 pts
W.A. Parish U8 โ€” 7FA Major Inspection$3.6M14%8%-5.8 pts
S.R. Bertron โ€” Forced Outage Support$1.2M22%21%-1.0 pts
Lessons from past work3 captured ยท from Exec
S.R. Bertron โ€” Forced Outage Support2022-04-12FORCED OUTAGESTANDBY CREWMARGIN

Helped24-hour mobilization on a forced outage printed premium margin โ€” being the crew that can respond is the moat.

Next timeKeep a standby crew costed into the rate so forced-outage premium work stays profitable.

Midlothian U1 โ€” 7FA Hot Gas Path2023-04-15LUMP SUMPARTS LEAD TIMESCHEDULE

HurtLump-sum HGP without confirmed transition-piece lead time โ€” parts arrived late, crew idled 2 shifts. The fade was schedule, not execution.

Next timeDon't take lump sum on an HGP until parts lead time is confirmed in writing; otherwise price the schedule risk.

W.A. Parish U8 โ€” 7FA Major Inspection2022-06-23SCOPEBORESCOPECHANGE ORDERS

HelpedCoastal's outage planner gave us early borescope access โ€” we caught R1 bucket distress before mobilization and re-planned the disassembly.

HurtEven with early access the added bucket scope grew disassembly ~4 days; the bid hours didn't carry that contingency.

ClientPlant manager valued the daily findings reports and no-surprise change orders.

Next timeMake confirmed pre-outage borescope access a hard gate before bidding 7FA major hours.

Opportunities (2)
OpportunityStageDivisionsValueExp margin
Feedwater heater replacementWonMechanical$700k13%
ST hot reheat valve repairQuoteMechanical ยท Specialist$1.1M14%